  • Series of open pits that previously provided the baseload of ore feed from Dalgaranga
  • Stratigraphic/shale-associated gold mineralisation
  • Extensions to mineralisation identified at Gilbey’s North and Gilbey’s Footwall
  • Expectation that ore feed from Gilbey’s pits will supplement higher-grade production from Never Never/Pepper

Never Never

  • High-grade gold discovery that forms the centrepiece of Spartan’s mine re-start plan
  • 1.48Moz Mineral Resource grading 8.07g/t gold
  • 600m from the processing plant
  • Structural, fold and/or shear-hosted gold mineralisation
  • Open at depth, with drilling continuing

Plant

  • 2.5Mtpa carbon-in-leach processing plant with sizeable gravity circuit
  • 5-year-old infrastructure – crusher, mill, power station, all in great condition
  • In high-state Care & Maintenance status – mill rotated, greasing system operating

Admin

  • Well qualified Board and management team with significant experience in the Australian gold sector and mining industry
  • Robust capital structure
  • Supportive shareholder base

Juniper Decline

  • Construction of new underground exploration drill drive underway
  • Underground drill platforms to expand high-grade deposits and target new discoveries
  • Designed to also support future mine production activities

Pepper

  • New high-grade discovery
  • Located between Never Never and Gilbey’s
  • 0.43Moz Mineral Resource grading 7.66g/t gold

High-grade
Gold in Western
Australia

  • Flagship 100%-owned Dalgaranga Gold Project in WA’s Murchison Region.
  • Delivering high-grade ounces in front of established infrastructure.
  • High-grade Never Never and Pepper Deposits – one of Australia’s most exciting new gold discoveries, with a combined high-grade underground Mineral Resource Estimate (MRE) of 2.324Moz (7.76Mt @ 9.32g/t) – including an Indicated Resource of 1.867Moz (5.92Mt at 9.81g/t) – and still open.
  • Recent high-grade Freak discovery made in November 2024 immediately adjacent to Never Never and Pepper – the next high-priority target being drill tested.  
  • All high-grade underground resources located within 1km of a relatively new 2.5Mtpa CIL processing plant and infrastructure (currently on care and maintenance, originally commissioned in May 2018).  
  • Updated (December 2024) MRE for the Dalgaranga Gold Project of 15.90Mt at 5.61g/t gold for 2.869Moz, all located on granted Mining Leases and within 3km of the processing plant with 75% of contained ounces classified as Indicated.
  • Underground exploration drill-drive underway, with a twin decline access for the establishment of underground drilling platforms to in-fill and extend the Never Never, Pepper, Freak, Four Pillars and West Winds deposits. Development is planned to continue to advance the access to the ore zones once the exploration decline has been completed.
  • All key regulatory approvals received to commence underground mining and processing operations at Dalgaranga
  • Aggressive drilling focus to deliver further growth, with 90,000m of drilling planned for CY2025 – 25km from surface and 65km from underground.

High-grade
Gold Focus

Spartan Resources is focused on delivering high-grade ounces at its flagship Dalgaranga Gold Project as the foundation for a sustainable long-term operating plan aimed at delivering strong returns for all key stakeholders.

Leveraging off the modern infrastructure at the Dalgaranga site, which includes a fully established and self-contained gold mine, 2.5mtpa carbon-in-leach processing facility, camp accommodation and airstrip, the Company is pursuing an aggressive growth strategy driven by near-mine exploration, completion of a re-start Feasibility Study and the ultimate recommencement of mining and processing operations at Dalgaranga.

The current focus of this strategy is drilling, targeting extensions at depth and along strike of the combined high-grade underground 2.324Moz Never Never and Pepper Gold Deposits.

Our Projects

ASX Announcements

..
All Announcements

Presentations

..
All Presentations

Our Team

 
Simon Lawson
Managing Director
 
David Coyne
Executive Director & Joint Company Secretary
 
Deanna Carpenter
Non-Executive Director
 
Mark Hine
Non-Executive Director
 
Tejal Magan
CHIEF FINANCIAL OFFICER
 
Craig Jones
CHIEF OPERATING OFFICER
 
Anna Neuling
Non-Executive Director

Stay updated with Spartan news & events. Join mailing list today.

Spartan Resources
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.